To obtain the Project plans and specifications, please review the Notice to Contractors document below and click on the link found under paragraph (1)b.  All Contractors are required to complete the Plan Holders Affidavit prior to accessing the project documents. 

If you have specific questions related to the project, please submit your RFI's in writing to DPW_middlefieldrdproject@smcgov.org, mraman@smcgov.org and cchoi@smcgov.org.  All RFI requests are due by December 2, 2020.  The County will not accept RFI's after December 2, 2020.  County will provide responses within five (5) working days.  The County anticipates releasing responses to RFI's no later than December 9, 2020.

Bid Opening is scheduled for Tuesday, December 15, 2020 at 2:30PM.