The bridge project is located along Mirada Road in an unincorporated community of Miramar and in the City of Half Moon Bay, within San Mateo County, approximately 0.15 miles west of State Route 1. View a Google map.
About the Project
The Department is working to design a project to replace the deteriorating pedestrian/bicycle bridge over Arroyo de en Medio in its current location and reinforce the banks adjacent to the bridge. The project area extends along the bluff below Mirada Road, from Medio Avenue to the Mirada Road cul-de-sac south of the existing pedestrian bridge. The project proposes to retain the current alignment of the pedestrian/bicycle bridge and trail.
Project Status
Bridge Closure:
Bridge was closed on July 27, 2020 due to the severe rusting and poor condition of the bridge (see Bridge Closure Announcement).
The detour route is opened on September 21, 2020 after Public Works obtained Caltran's approval to provide a detour route on HWY 1 shoulder within their right of way.
Design:
Completed 65% design, June 2020
Permits submitted to regulatory agencies, June 2020
Anticipated 100% design by December 2020
Construction:
April 2021 (permits dependent)
120 working days (est.) (bridge fabrication may extend construction window)