Construction Activities, Updates, & Related Documents

Construction Week #03 - Updates (Week of May 28, 2018)

  • The Contractor will not be working on Monday, May 28, 2018 (Memorial Day)
  • Additional concrete valley gutter will be poured on the south side of the street (between Edison Way and Park Road)
  • Excavation for the 3' wide concrete valley gutter on the north side of the street (between Edison Way and Park Road) is scheduled to begin

***IMPORTANT REMINDER*** - The No-Parking restrictions remain in effect on 7th Avenue as posted, between the hours of 8 am and 5 pm, Monday through Friday. To avoid having your vehicle(s) towed, do not park on the street where it is posted for no parking. The equipment used for the road project are large and the street is relatively narrow. Complying with these parking restrictions helps the contractor complete the scheduled work, eliminates the need to tow cars, and reduces potential damages to vehicles. We appreciate your assistance with this issue as we work to complete this Project.

Construction Week # 02 - Updates (Week of May 21, 2018)

  • Continue Excavation work for the 3' wide concrete valley gutter (between Edison Way and Park Road)
  • First concrete pour of a section of the 3' wide concrete valley gutter (between Edison Way and Park Road)

Construction Week # 01 - Updates (Week of May 14, 2018)

  • Mobilization of Contractor’s Equipment & Appurtenances
  • Installing Traffic Control Devices
  • Potholing for Utilities